Headwall Repair for Yosemite Bridge Access to Plaza Tower One

Active Project Status


Update:

 

September 2017

Project Description: This project consists of repairing the deteriorated south headwall and surrounding bridge walls at the Yosemite Overpass west vehicular tunnel into the Plaza Tower One.

Project Manager:

John Wannigman


Project Status: Staff contacted the design-build team to schedule construction.  It is anticipated that the repairs of the south tunnel face and the ceiling in the tunnel will begin in November and take approximately 5 weeks to complete.  This will repair the areas in most need of repair.  Ultimate repairs will take place once the final design of the pedestrian connection to the Arapahoe Station from Yosemite Street and Peakview Avenue is determined.  The CIP project for the pedestrian connection is identified in the 2018 CIP.