Pavement and Concrete Rehabilitation

Active Project Status



Updated:

  December 2017


Project Description:

Provide reconstruction of Village streets and trails as well as surface treatments to prolong the life of Village pavements. This program also provides for the replacement of deteriorated concrete trails and concrete along Village streets.


Project Manager:


Wanda DeVargas - Concrete Program
John Wannigman - Pavement Program

Concrete Program

-
Canon Villas subdivision, E. Progress Circle (Monaco) and installation of ADA ramps at Yosemite/Radcliff were complete. Crews plan to continue with installations at miscellaneous locations and punch list items during the month of September.  

Pavement Rehabilitation Program

- Project is complete.  2018 PRP inventory inspections have been completed and negotiations have begun with Brannan Sand & Gravel for a possible contract extension.

Pavement Preservation Program

- Brannan S & G has a tentative start date of May 30. Boston St. was removed from the scope, and design work by JR Engineering has begun for grade changes at the north end new Belleview.

Trail Rehabilitation Program

The 2017 TRP - all drainage installations and trail surface work on the Holly St. Trail and the King Soopers Trail have been completed.   Landscape restoration to be completed in the spring, 2018.


Rejuvenator Sealing 

 - The 2017 Rejuvenator Seal Project is currently underway on Orchard Road West of University Blvd. and Quebec between East Berry Ave and East Progress Place with a projected completion date of September 16th.

Gravel Road Rehabilitation Project 

 - Test sections are all in place and being monitored for performance.