Goldsmith Gulch - Orchard at Silo Park

Active Project Status



Updated:

March 2016

Project Description:

The project includes the replacement of the existing culvert with a larger structure to reduce the potential for overtopping of Orchard Road in a 100 year event. The schedule is based on anticipated funding from the Urban Drainage and Flood Control District (USFCD). The design will be completed in 2016 with construction beginning in 2019.

Project Manager:

Wanda DeVargas


Project Status:

UDFCD is generating the IGA for the project design and anticipates Board approval in March 2016. Upon approval, the IGA will be sent to staff for City Council execution. A pre-design meeting and field walk through is scheduled for April to discuss the project scope and schedule.