Village Greens Park Phase IV

Active Project Status



Updated:

 June 2017

Project Description:

Project includes the addition of amenities to the entry to the existing disc golf and mountain bike courses to include a shelter, picnic area, and restroom.

Project Manager:

 Dave Foster

Project Status:

The restroom building was publicly bid in May and has been awarded to the Public Restroom Company. Staff is currently reviewing submittals from the contractor to coordinate the final design of the restroom. The restroom building is scheduled to be installed in November of 2017 as part of the first phase of construction. Staff continues to coordinate with Architerra Group on the overall improvements and construction documents are underway.