Orchard Hills Park Irrigation Upgrade

Active Project Status



Updated:

 June 2017

Project Description: During our punch list walk and pressure testing, numerous items were noted for correction on the irrigation installation, and the mainline did not pass the required pressure test. Most of the correction items have been fixed, however, Land Ethics is having difficulty getting the mainline to pass the pressure test. This project is now substantially past the deadline for completion, and Land Ethics has been notified to complete the project by this week or the City would start assessing liquidated damages.



Project Manager:

Suzanne Moore

Project Status:

This project is approximately 50% completed. Weather and cold temperatures have caused some delays, but the project is progressing on schedule and anticipated to be complete by mid-March.