Active Project Status

Updated:  July 2016

Project Name:  Synthetic Turf Field at Village Greens Park

Project Description:  The project entails converting Field 11 at Village Greens Park into a synthetic turf to increase field availability.

Project Manager:  Dave Foster

Project Status:
Construction is scheduled to begin with FieldTurf USA in August. Based on the geotechnical report, it was determined that an upgraded liner is needed to prevent water infiltration into the sub-grade, and consequent swelling.