As this project is approaching completion by the end of June, work planned for the week of June 18 is as follows:
* Final paving on Long Court, Fox Trail, Jackson Street, and north of Long Road;
* New sidewalk along the south side of Orchard Road from Columbine Way to the shopping center to the west;
* Roadway pavement striping and signage of side streets at Fox Trail and Long Court;
* Work will continue on the Long Lane/Orchard Road island; and
* Overall landscaping continues throughout the project limits.
All work is weather permitting. During these activities, the road will remain open for travel with one-way flagging operations as necessary to assure safety. For more information on the project please visit the project website at LongRoadReconstruction.com or contact John Wannigman, Project Manager at 303-708-6139.